mropinionated.com


Welcome to Mr.Opinionated.com! jan feb mar apr may jun jul aug sep oct nov dec jan main
12/30/04 - HUGE Picture and Theater Update (4) (11) (3) (5) (2) (9) (stage)
As we round the final stretch there is a lot of activity at the house these days. Paint, carpet and light fixtures are approximately 98% complete. Some of our fixtures were backordered so we have a temporary light for now and others were still being hung as we were leaving for the day. The basement carpet was also being completed when we left, and the stairwells were last on the list. We're still waiting on one last order of tile for our master shower, but the bathroom floors are now close to being done. HVAC, Plumbing, and Decking are all being worked on as I type this, and hopefully completed soon. I'm also told that our countertop material has been delivered to the fabricator and can be installed as soon as Monday. As you may have gathered, the 31st drop-dead date has been extended. Now its January 7th. Fingers are crossed, but things look positive!

12/18/04 - Theater Update (paint)

12/15/04 - Picture Update (4) (15) (3)
Only a few weeks left in 2004, but things are moving nicely. The cabinets have all been installed, but unfortunately the master bathroom cabinets were the wrong color. The top floor and basement have been painted, and if you look closely at some of the pictures you can see the lights on. All the trim has been installed and is waiting for painting. Carpeting, light fixtures and bathroom tile seems to be all that's left.

12/07/04 - MAJOR Picture and Site Update (3) (4) (3) (4) (5) (4) (2)
With a drop-dead date of Dec. 31st, the builder races against the clock to get all the remaining items completed.  The goal is to receive approval by the inspector for a Certificate of Occupancy (CO), which would allow us to move into our new home.  The race is going to be tight as we continuously learn about material delays and difficulties with some of the trades, but it seems like it might be doable.

Sorry for such a large update, but we've been busy with our final selections. Lighting, carpeting, and decking for the house, along with rings and tuxes for the wedding, have basically consumed all our time. With things moving along at a much faster pace, I'll try to post an update weekly. All of the drywall has been sanded and primed and the upstairs base, window, and door trim has been installed. Painting of all the trim and doors has also started upstairs while the tile guys completed the first floor. With that done, trim, cabinets and doors can be installed on the first floor. Unfortunately, tile seems to be the one item delayed the most, so work on the other bathrooms must wait. With our unusually warm December weather, we're going to try to get a deck built too.

On the Site side of things, I've nearly run out of web space (I only get 500MB), so I've compressed all the original images down to a more reasonable size. For those on dial-up, this should mean faster download times. If there is a picture you'd like to see the original for, shoot me an email and I'll send it to you.

Enjoy your visit!

 -Brian


Note: I will attempt to update the site on a weekly basis or when time allows. Please check back for updates.