06/30/04 - Mass Picture Update (4) (3) (10)
The basement, garage and front stoop have finally all been poured! In the pictures, you can see the progression of final touches on plumbing and then wet and dry shots of the garage and basement. Next the framers will return to complete the stairs, frame out the basement, and put any finishing touches on framing work on the other two floors. The HVAC guys should also be coming back around the same time to install the furnaces and finish runing ductwork. Once the basement is framed, the electrician and structured wiring guys can complete their portions so that the walls can be insulated and dry walled.

06/22/04 - Picture Update (7)
The basement has been completely leveled off with stone as we await concrete. The plumber has one last pipe to lay before that can occur, but he was pulling into the driveway as I was leaving. Soon we will have a basement floor!

06/18/04 - Picture Update (7)
PROGRESS! After waiting for schedules to align, there is finally some action occurring at the house today. A large load of filler stone was delivered this morning to begin filling the basement and garage in preparation for the concrete to be poured. The electrician has also started on the 2nd floor and is working his way down. Several can lights and electrical boxes have been installed and most of the upstairs wiring is complete.

06/16/04 - Site Update
For those interested in our wedding plans, I've updated the wedding link to include some information.

Also hoping to see more action on the house as we've been told by the builder that we're next on the list for the concrete guys.

06/10/04 - Picture Update (3)
The shingles are now complete which should help keep things dry with all this rain we've been getting lately. Hopefully, however, the rain will allow the concrete guys to pour the basement. (On sunny days they pour driveways and sidewalks)

06/07/04 - Picture Update (3)
A little more progress has been made on the shingles and HVAC. I believe the HVAC guy is waiting on the basement to be poured before completing his work. (Although that doesn't explain why the shingles are taking so long).

06/01/04 - Picture Update (4)
Most of the shingling has been completed and work on the HVAC has started as well. We're crossing our fingers for rainy weather so the concrete guys will come pour our basement. (If the weather is nice, they've got sidewalks and driveways to pour instead.)

Enjoy your visit!

 -Brian


Note: I will attempt to update the site on a weekly basis or when time allows. Please check back for updates.