05/28/04 - Picture Update (9)
The shingles have been delivered and the skylights installed as work begins on the roof. No word on the basement yet, but some ducting and sheet metal have been collecting in a corner and growing. Any day now.

05/25/04 - Picture Update (2)
Just a small update today. The tub/shower unit has been installed in the reconfigured Jack & Jill bathroom and the jacuzzi has been installed in the master bath.

05/19/04 - Picture Update (5)
After delaying a couple weeks to make plumbing decisions (colors, faucets, toilets, etc.), the house is once again a bustle of activity. The framers are finishing up any final internal woodwork that needs to be completed, while the plumbers are installing PVC and copper piping throughout the house. Once plumbed, the basement floor will be poured, allowing HVAC work and basement wall framing to begin. Wiring, both electrical and structured (cable, phone, and network), will start shortly afterwards. Also awaiting delivery are the shingles and the stone siding.

05/06/04 - Picture Update (7)
The driveway is really starting to take shape now with the load of stones that were delivered. The greatroom windows have also been delivered and installed and all that is left now is the breakfast room. Plumbing should be completing over the next week or so and HVAC and electrical come next. Only a few months left!

Enjoy your visit!

 -Brian


Note: I will attempt to update the site on a weekly basis or when time allows. Please check back for updates.